We have received the following advance notice on the gas main replacement work and road closures that are planned:

As part of the ongoing gas main replacement work throughout Cardiff, Wales & West Utilities will be closing a section of Heol-y-Deri and Rhiwbina Hill to carry out the final part of the Rhiwbina connection. Heol-y-Deri will be closed from its junction with Pen-Y-Dre/Beulah Road to its junction with Lon Isa from 8.00am on 27th January until 18.00pm on 16th February.

Following on from the Heol-y-Deri closure, the team will need a 5 day closure to do the final connection on Rhiwbina Hill by the little roundabout at the junction of Pantmawr Road, this will be from 8.00am on the 17.02.18 until 18.00pm on 21.02.18.

Wales & West Utilities will be carrying out a full letter drop to all local residents with diversion routes clearly sign posted and all bus operators and emergency services will be full advised.